Projects

One of the UK’s leading Multi-Utility Civil Engineering Services

A453 Road widening works – Stage 2 (Ratcliffe to Willoughby)

Project overview: Diverting 132kv apparatus away from location of proposed road construction works as it passes Ratcliffe on Sour Power Station

Scope of works:

Installation of approx. 3.2km of 132kv double circuit & all associated works, to include – Constructing Double Circuit Joint Bays

Construction of link boxes & fibre pits

Cable pulling