Projects

One of the UK’s leading Multi-Utility Civil Engineering Services

Coventry South to Whitley

Project overview: to replace the following existing fluid filled cable circuits with new circuits as detailed: 2nr x 132kV XLPE Cable Circuits between Coventry South & Whitley Substation – approximate route 5.8km

Scope of works:

Carry out the excavation of trenches, installation of ducts and backfill to final reinstatement specification

Removal and disposal of surplus excavated materials off site.

Construction of Double Circuit Joint Bays x 11

Construction of link boxes x 22

Construction of fibre pits x 18

Pulling of sub ducts into fibre pits